111 Jacket pin piles for Hai Long OWF – Phase 1
111 JACKET PIN PILES FOR HAI LONG OFFSHORE WIND FARM – PHASE 1
Between April 2024 and August 2024, the CAPE VLT-640 was used to install 111 out of 219 jacket pin piles with a diameter up to 3.5 meter and a maximum length of 93.3 meter for phase one of the Hai Long Offshore Wind Farm in Taiwanese waters.
In 2025 the second phase will start around March 2025 to install the remaining piles. The Green Jade, Taiwan’s first 4,000t crane vessel with DP capabilities, of CDWE was used for the project. 12 piles, stacked in 3 layers, were taken on the deck to install 4 jacket locations per trip.
Main reason to choose for using the CAPE VLT was to prevent pile run. However, the efficiency of using the CAPE VLT was proven during the project as well, with the quickest time of 7 minutes to drive one of the pin piles up to 35m penetration depth.
Application details
Pin/jacket pile installation
Pin piles
36-56m
35m
7min
PILE DETAILS
Pin piles
Straight
93.3m
Up to 418t
65mm
3.5m
3.5m
111
PROJECT DETAILS
Apr ’24 – Aug ’24
Taiwan Strait
Taiwan
Hai Long Offshore Wind Farm, Taiwan
Offshore Renewables
Offshore Wind Turbine
Hai Long Wind Power
CDWE (DEME offshore & CSBC Corporation)
Offshore Heavy Lift DP3 Installation Vessel
Green Jade, CDWE
Dynamic Positioning
Main Reasons for solution choice
CAPE VLT-640
CAPE VLT-640
640kgm
989t
vibro
lifting
technology
Discover how its unique features will uplift your next project; download the vibro lifting technology guide.