12 pontoon piles Wilhelmshaven

February 5, 2025
In June 2024, Ballast Nedam successfully installed 12 access pontoon piles at Wilhelmshaven in northern Germany using the CAPE VLT-160 and S-150 impact hammer. The entire project was completed in less than two weeks.

8 Jacket skirt piles for Hai Long Sub Stations

January 21, 2025
In 2024, the CAPE VLT-640 Tandem was deployed to install 8 piles with a diameter of 4.4 meter, a length of 103.5 meter and a maximum weight of 935t for two offshore sub stations for phase one of the Hai Long Offshore Wind project in Taiwanese waters.

78 monopiles for Coastal Virginia OWF – phase 1

October 28, 2024
Between May and September 2024, the CAPE VLT-640 Quad was used to install 78 monopiles for the Coastal Virginia Offshore Wind Farm in U.S. waters. Each monopile had a bottom diameter of up to 8.5 meters, a length of up to 82 meters, and a mass of up to 1,700…

29 Flanged monopiles for Moray West OWF

September 17, 2024
Between February 2024 and April 2024, the CAPE VLT-640 Quad was used by installation contractor DEME on board of its Offshore Heavy Lift DP3 installation vessel Orion to install 29 flanged monopiles with a bottom diameter up to 10 meters and a length of up to 91 meters for the…

12 Flanged monopiles for Moray West OWF

September 9, 2024
Between November 2023 and March 2024, the CAPE VLT-640 Triple was used by installation contractor Boskalis on board its Heavy Lift Vessel Bokalift 2 to install 12 flanged monopiles with a bottom diameter of up to 10 meters and a length of up to 91 meters for Ocean Winds' Moray…

188 pin piles for Formosa 2 OWF

February 13, 2023
Starting in 2020, a CAPE VLT-320 has been used to upend and drive pin piles with a diameter of 96 inches through a pre-piling template at the Formosa 2 Offshore Wind project.