Drive and extract a 6.5 meter diameter monopile October 28, 2019 In 2019, a CAPE VLT-320 Tandem was used to drive and extract a 6.5 meter diameter monopile on the Hollandse Kust Zuid Offshore Wind Farm.
20 monopiles for Formosa 1 OWF October 15, 2019 In 2019, the CAPE VLT-320 Triple was used to install 20 tapered monopiles with diameters up to 8.4 meter for the Formosa I OWF.
3 pin piles for Soft Yoke Mooring System September 20, 2019 In 2019, the CAPE VLT-320 was used to upend and install three 96 inch pin piles with a length of 45 meter at a water depth of 20 meter.
9 subsea jacket piles in Gulf of Mexico August 13, 2019 In 2019, the CAPE VLT-320 was used to upend and install nine 64 inch jacket piles with a length of over 100 meter at a water depth of 60 meter.
4 pin piles for seabed structure June 10, 2019 In 2019, the CAPE VLT-80 was used to upend and install four 60 inch diameter pin piles with a length of 18 meter and weighing 22 tonnes.
6 anchor piles for FPSO Mooring system November 14, 2018 In 2018, the CAPE VLT-80 was used to upend and install six 60 inch diameter anchor piles with a length of 30 meter, in a waterdepth of 26 meter.
4 through leg pin piles for a wellhead platform October 17, 2018 In 2018, the CAPE VLT-80 was used to upend and install four 1,829mm diameter through leg jacket piles in a waterdepth of 32.5 meter.
Monopile installation on Amalia Offshore Wind Farm September 3, 2018 In 2018, the CAPE VLT-320 Tandem was used to upend and install a 4 meter diameter monopile with a slip joint at the Amalia Offshore Wind Farm.
Free hanging monopile installation test August 7, 2018 In 2018, the CAPE VLT-320 Tandem was used to upend and install a 6.5 meter diameter monopile at the Maasvlakte 2 in Rotterdam, the Netherlands.
4 tapered pin piles for jacket foundation November 14, 2017 In 2017, the CAPE VLT-320 was used to upend and install 4 pin piles with a length of 77 meters for a jacket foundation.