4 PRE-PILED JACKET PILES WITH POSITIONING TEMPLATE

DATE: April 1, 2025

4 PRE-PILED JACKET PILES WITH POSITIONING TEMPLATE

In April – May 2023, CAPE Holland equipment was used to install four 84 inch pre-piled jacket piles. What makes this project special is that thanks to utilising the CAPE VLT, the pre-piling template did not need to support the piles and could therefore be a simple single layer positioning template.

The CAPE VLT-320 was used to upend the piles directly from a supply vessel and drove them straight through the positioning template on the seabed. Verticality was controlled by moving the CAPE VLT-320 with the crane hook whilst vibrating.

After having installed all four piles to the required depth, a hydraulic impact hammer (also supplied and operated by CAPE Holland) was used to drive the piles to final penetration.

Application details

Application

Pre-piled jacket piles

Water depth

38m

Penetration

CAPE VLT 18-20m / S-500 to final penetration

PILE DETAILS

Pile type

Jacket piles

Pile length

38.8m

Pile weight

130t

Pile wall thickness

50mm

Pile diameter

84inch

No. of piles

4

PROJECT DETAILS

Period

April-May 2023

Market

Oil & Gas

System/end usage

Oil & Gas production

Type of vessel

Floating Installation Vessel

Mode

Anchors

Main Reasons for solution choice

UPENDING, LIFTING, DRIVING IN SINGLE OPERATION

SUBSEA COMPATIBLE

CONTROLLED INSTALLATION

SELECTED EQUIPMENT

CAPE VLT-320

Equipment configuration

CAPE VLT-320

Eccentric moment

320kgm

Max. line pull

500t

vibro
lifting
technology

Discover how its unique features will uplift your next project; download the vibro lifting technology guide.

YOU MIGHT BE
INTERESTED IN