With CAPE Holland’s growing activities in the USA we have moved our equipment to a new workshop in Dayton, Texas. The proximity to the regional office located at City center in Houston brings CAPE Holland more flexibility to better serve the region.
CAPE Holland is excited to announce that we have been awarded a contract by installation contractor Boskalis for the delivery of a CAPE VLT-640 Triple spread.
Starting in 2020, a CAPE VLT-320 has been used to upend and drive pin piles with a diameter of 96 inches through a pre-piling template at the Formosa 2 Offshore Wind project.
From August 2019 - December 2022, a CAPE VLT-80 was used for the installation of 60 jacket piles for the Absheron EPS platform in the Caspian Sea, offshore Azerbaijan.
In 2022, the CAPE VLT-80 was used to upend and install 65 combi wall piles with a length of 29.25m for the renovation of the Royerssluis/lock and Oosterweelknoop in Antwerp, Belgium.