News
and highlights

Huge savings in pre-piling with CAPE VLT

April 8, 2025
One of the main benefits of the CAPE VLT is that together with the pile hanging in the crane, it is acting as a high weight on a piece of string (or a clump weight), so by the laws of physics, it wants to be vertical. This also supports the…

12 pontoon piles Wilhelmshaven

February 5, 2025
In June 2024, Ballast Nedam successfully installed 12 access pontoon piles at Wilhelmshaven in northern Germany using the CAPE VLT-160 and S-150 impact hammer. The entire project was completed in less than two weeks.

8 Jacket skirt piles for Hai Long Sub Stations

January 21, 2025
In 2024, the CAPE VLT-640 Tandem was deployed to install 8 piles with a diameter of 4.4 meter, a length of 103.5 meter and a maximum weight of 935t for two offshore sub stations for phase one of the Hai Long Offshore Wind project in Taiwanese waters.

29 Flanged monopiles for Moray West OWF

September 17, 2024
Between February 2024 and April 2024, the CAPE VLT-640 Quad was used by installation contractor DEME on board of its Offshore Heavy Lift DP3 installation vessel Orion to install 29 flanged monopiles with a bottom diameter up to 10 meters and a length of up to 91 meters for the…